Introduction

After you have issued a credit note for an invoice (for details, see the Add a credit note guide), you can edit it manually using one of the following scenarios.

Panel
panelIconId1f4a1
panelIcon:bulb:
panelIconText💡
bgColor#E3FCEF

To locate the required credit note, use the Invoice Type is filter.

Locate CN.png

Correct selected items in a credit note

You can change the value of a particular item in an invoice and have it reflected in task receivables.

  1. Open the required credit note in edit mode.

  2. Scroll down and select the Items tab.

    Correct items 1.png

  3. Click the (blue star) ‘Edit’ icon. The Corrective items popup will be displayed. You can make the required corrections in the New Values column by changing the Quantity, Unit, Rate, Discount / Surcharge, and Tax Rate fields.
    (blue star) Those changes will not affect task receivables.

    Corrective items.png

  4. Click the Save button.

(Optional) Edit the receivables

Changes in receivables will be reflected in values calculated for tasks but will not affect the values of items. Items are part of an invoice, while tasks and receivables are parts of a project.

Note

Ensure that the ‘Auto-Calculate Total Agreed’ checkbox in the ‘Receivables' tab is selected. Otherwise, changing values for receivables will not affect the Total Agreed value.

Receivables Smart.pngReceivables Classic.png
  1. On the credit note page, select the Tasks tab.

  2. Scroll down to the Receivables section.

    Receivables.png

  3. Click the (blue star) ‘Edit’ icon. The Task Receivable popup will be displayed.

    Task receivables.png

  4. In the New Values section, enter the required values.
    (info) For CAT receivables, you can correct the values for particular match types in the CAT grid.

  5. Click the Save button.

  6. On the credit note page, check if the recalculated Task Values and Net Total are correct.

  7. Click the Save button at the bottom of the credit note page.


Remove tasks from a credit note for further use

If you have mistakenly included a task on an invoice, you need to unlock it so it can be added to a different invoice. However, if you have issued a credit note for this invoice, you must first remove the task from the credit note.

Remove a task without changing receivables

  1. Open the required credit note in edit mode.

  2. Scroll down and select the Tasks tab.

    Remove task.png
  3. Click the (blue star) ‘Remove’ icon in the required task line. The task will be marked with a strikethrough.

  4. Click the Save button. The task will be automatically removed from the original invoice and ready to be invoiced again.

Remove task2.png

Remove a task and change receivables

Info

Remove tasks first, then change receivables. If you make changes in receivables before unlocking tasks, all the changes made in receivables will be discarded.

  1. Remove one or several tasks as described above.

  2. Open the project linked to the task and edit receivables there.