Table of Contents |
---|
Page Properties |
---|
Introduction
This article provides solutions to the most common issues with Costs & Metrics reports.
...
Solution: Remember that, by default, the Costs & The Metrics report retrieved from specific projects is based on data from the last correctly generated costs in those projects, i.e. those which did not contain errors or warnings after the generation process – red and yellow symbols next to entries in Project editor → Estimates → Costs.
Note |
---|
IMPORTANT! Note that there is an Include costs with warnings in Cost and metrics reports option, which enables cost entries with WARNINGS (yellow) in reports as well. |
After you change the project settings or cost settings, make sure that the costs are generated again before you attempt to generate the report. Generating a report does not automatically generate costs if any costs were correctly generated in the past, in a specific project.
...