  1. As a Project Manager or an Administrator, go to the Users User list, and click the user that is intended to perform the alignment.

Note

IMPORTANT!

Remember that this user needs to have the Project Manager role.

...

  1. Go to Access rights Translation memory, and add the Align access right to the correct column in the tab screen and click the Save button.

...

  1. As a user with the Align access right, go to TM Align.

...

  1. Enter a Reference name, select Source and Target languages, select Source and Target files, select Customer and then select additional options if needed (item “5”) → click Align.

...